Mercer Chorus Fibre Install

Project Type: Fibre Network Installation

Project Overview:

A 3.5km fibre installation project that combined drilling, pit setup, duct installation, and traffic management into a full turnkey package. The project focused on seamless delivery with minimal community disruption.

Key Features:
  • 3.5 km microduct drilling for fibre installation
  • Turnkey traffic management to maintain community safety
  • Integrated delivery combining drilling, pit, and duct setup
  • Efficient scheduling and high safety standards
Scope of Work:
  • Microduct Installation: 3,500 meters laid as per design
  • Pit & Manhole Installation:
    • 1 × Sika Pit
    • 1 × SGLB2436 Channell Pit
    • 1 × Chorus Manhole
  • Existing Duct Location: 100 meters identified and located
  • Rural Access Tub Installation: 1 × U-MDK322
  • Straight Joints for Microducts
  • Berm Reinstatement and Traffic Management
Execution Highlights:
  • Hydro excavation and slot trenching for precision work
  • Onsite duct management ensuring organised and efficient installation
  • Adherence to safety protocols and coordination among teams
  • Completion of Ribbonet jointing and ABFAT for full network integrity